Large-scale masterplan · Greenwich

Bugsby's Way

Location
Greenwich, South East London
Scale
1,465 homes over multiple phases
Services
Delivery strategy · Phasing · Logistics and craneage · Health and safety planning
Illustrative aerial sketch of the Bugsby's Way scheme beside the IKEA store and the A102

The scheme

A delivery strategy for a multi-phase scheme planned over the car park of a trading IKEA store, where the parking had to stay open throughout.

The question

Can 1,465 homes be built on top of a working retailer's car park without breaking the parking its lease requires? If so, in what order?

What we did

  • Agreed with IKEA how the parking its lease requires would be kept available for the whole build.
  • Divided the car park into three areas, each taken through the same sequence: build the podium, build the homes above it, then hand back the parking beneath.
  • Positioned the cranes and planned logistics around a store that kept trading.
  • Coordinated health and safety planning for tall buildings, several cranes working together and openings through slabs.

Why it mattered

The scheme only worked if the store could keep trading. A phasing strategy that protected the parking gave the developer and the retailer a route both could sign up to.

Have a site, a scheme or a programme to discuss?

Tell us what you are working on, the decision you need to make and where support would help.

Discuss a project

Email phil@bailyconsult.co.uk or call 07814 717088