The scheme

756 homes over a full-site basement, with London Underground tunnels running beneath, a former gas holder, and a masterplan full of competing access rights.

The question

How do you get a large build-to-rent scheme built and occupied on a site where the planning conditions, the ground beneath it and the neighbouring developers all limit what you can do, and when?

What we did

  • Agreed changes to the planning conditions with the master developer, so that occupation would not be held back.
  • Untangled the access rights the master developer had given other developers across the site, which allowed the construction routes and the programme to be fixed.
  • Planned a basement spanning the whole site, with London Underground tunnels below it.
  • Allowed for the former gas holder in the plan for the site.
  • Brought the build-to-rent operator's requirements into the delivery plan for around three-quarters of the homes.
  • Prepared a detailed Project Execution Plan setting out logistics, crane positions, deliveries and façade installation.

Why it mattered

Unless the conditions were changed and the access rights resolved, the homes could not be occupied on time. Sorting both early gave the scheme a programme it could actually be built to.

Images

Have a site, a scheme or a programme to discuss?

Tell us what you are working on, the decision you need to make and where support would help.

Discuss a project

Email phil@bailyconsult.co.uk or call 07814 717088